Non Destructive Thickness Measurement Of Asphalt Layers – A New Zealand Case Study

Aug 28, 2022 | Asphalt Pavement Investigation, Concrete Pavement Investigation

One of our innovative clients, WSP, was looking for a way to assess the thickness of asphalt layers during the construction process and easily report their findings. They wanted to do this non-destructively and in a manner that seamlessly integrated with the construction process.

These requirements and the accuracy needed led them to the MIT-SCAN-T3, an NDT device.

  • Accuracy of the MIT SCAN is ± (0.5% of measured thickness + 1mm).

The project was a 12 km long 4 lane expressway with a structural asphalt pavement. WSP’s role was acting as the client representative, for the Waka Kotahi NZ Transport Agency, ensuring complying quality was being achieved.

The MIT-SCAN-T3 uses reflectors inserted into the pavement during construction, hence the test is only suitable for situations where reflectors can be inserted into the pavement during the construction process.

In this case, WSP used both the 300mm and 120mm diameter aluminium reflectors. This gave them more flexibility with regard to when they were able to access the site.

The pavement structure was made up of the following:

Ideally, where they could get in early enough, they placed the 300mm diameter reflectors and measured the three successive layers of asphalt. The finish of the stabilised AP65 subbase was often uneven and made attaching the 300mm diameter reflectors difficult. Occasionally construction activities dislodged some of the reflectors before they could be paved over. WSP designed and 3D printed dowels that were glued to the bottom of the reflector and anchor fixed into the stabilised granular pavement. This significantly reduced the amount of glue required to hold the reflectors and almost completely eliminated the loss of reflectors caused by construction activities.

Figure 1 – 300mm reflector with the 3D printed dowel attached

WSP have since found a supply of off the shelf dowels and are currently using the larger of the two shown in the photograph below.

Figure 2 – Commercially available dowels

In section across the pavement, the initial thinking was to place reflectors in the middle and outer edges of each paving run. With reflectors placed at 40m cross section intervals it was too difficult to place and maintain seven reflectors so the layout was changed to placing a reflector near the middle of each run reducing the number of reflectors to three for each cross section. The general layout configuration is shown in the following diagram.

In the locations where the 300mm reflectors were dislodged, WSP used the 120mm diameter reflectors, placed on top of the AC20 layer and were able to measure the thickness of the AC14 layer and then the Epoxy Modified Open Graded Porous Asphalt (EMOGPA) wearing surface.

To provide greater coverage of the EMOGPA wearing surface thickness, 70mm reflectors were placed on top of the AC14 on cross-sections between the 300mm reflectors. This provided thickness measurements at 20m intervals.

The MIT-SCAN-T3 enables the quick location of the reflectors and then, the GPS located time stamped asphalt thickness reading is taken and recorded electronically. Data is transferred to the phone or tablet based MIT-SCAN-T3-APP, which enables you to:

  • Review the current measurements
  • Manage your measurement data
  • Create and send reports

Data can also be transferred to the PC-based MIT-Project-Software for data storage, presentation and geo-positioning of results.

The benefit of using the MIT-SCAN-T3 compared with traditional layer thickness measurement is that a very comprehensive coverage of asphalt thickness can be produced without cutting any core holes in the asphalt.

Cores may need to be cut to measure air void compliance in the asphalt, but if calibrated Nuclear Density Meter (NDM) thin lift gauge results are acceptable, or there is not a requirement to measure air voids, then there is no need to complete any destructive compliance measurements.

Other significant benefits of using the MIT-SCAN-T3 is the saving in time, personnel, and equipment to compile the layer thickness results.

Time is saved as the scanning can be completed as soon as the asphalt is sufficiently cool to run the MIT-SCAN-T3 over the surface. There is no need to wait until the asphalt is sufficiently cold enough to core.

The personnel saving is that the scanning can be completed quickly and efficiently by one person using the MIT-SCAN-T3. Coring would take much longer and would generally require two Laboratory technicians to complete the coring safely.

The equipment saving is the simplicity of use and cost of the MIT-SCAN-T3 compared to the use and cost of a coring rig.

The ZFG 3000 is an excellent tool and should be included in any professional contractors equipment list of assets. This tool should have a similar impact on the construction industry as the laser level. The ability to accurately and reliably measure this aspect of ground condition will improve the quality of the work and remove doubt as to the progress of the project.

I bought my ZFG 3000 and on the same day less than two hours later, it had paid for itself. Using this instrument, I was able to demonstrate scientifically, repeatably and independently the quality of the work that we had completed for our client. Ending the disagreement and creating an improved working relationship. Most jobs are not as confrontational as this was however, most jobs are built to a standard. The contractor can now measure as required, to know on site, at the time of testing if this standard is being achieved.

I strongly recommend the ZFG 3000 Deflectometer to any earthmoving, civil construction contractor. Good luck with your projects.

Jim Bassett

Managing Director, Bassearth Pty Ltd

I would hate to go back to doing the Plate Load Test using the old method using dial gauges. It would be so time consuming, not to mention manually recording and then processing all the results.

Daniel Pearce

Director - Pearce Geotech

Insitutek imports, sells and services, unique geotech equipment that has proved of great benefit to those who use it. It has a particularly beneficial role to play for those compacting soil in infrastructure projects.

David Palmer

Earthmover and Civil Contractor

Insitutek Blogs

It’s always rewarding when we can bring both our “test” and “improve” capabilities to the same project.

This was the case with a recent case study for the application of TERRA-3000®, our clay soil stabilisation product in the City of Ballarat, VIC, which we tested using the Light Weight Deflectometer.

A bridge approach transition zone is the area where a road or railway track transitions from the rigid structure of a bridge to the flexible embankment or road pavement, aiming to minimize abrupt changes in stiffness and potential issues like differential settlement.

The 5th International Conference on Transportation Geotechnics (ICTG), held in Sydney, marked a milestone in the geotechnical and transportation engineering community. Organized by the UTS Transport Research Centre (UTS-TRC), this prestigious event brought together over 450 delegates from 30 countries, making it a truly global gathering for experts in the field.