Non Destructive Thickness Measurement Of Asphalt Layers – A New Zealand Case Study

Aug 28, 2022 | Asphalt Pavement Investigation, Concrete Pavement Investigation

One of our innovative clients, WSP, was looking for a way to assess the thickness of asphalt layers during the construction process and easily report their findings. They wanted to do this non-destructively and in a manner that seamlessly integrated with the construction process.

These requirements and the accuracy needed led them to the MIT-SCAN-T3, an NDT device.

  • Accuracy of the MIT SCAN is ± (0.5% of measured thickness + 1mm).

The project was a 12 km long 4 lane expressway with a structural asphalt pavement. WSP’s role was acting as the client representative, for the Waka Kotahi NZ Transport Agency, ensuring complying quality was being achieved.

The MIT-SCAN-T3 uses reflectors inserted into the pavement during construction, hence the test is only suitable for situations where reflectors can be inserted into the pavement during the construction process.

In this case, WSP used both the 300mm and 120mm diameter aluminium reflectors. This gave them more flexibility with regard to when they were able to access the site.

The pavement structure was made up of the following:

Ideally, where they could get in early enough, they placed the 300mm diameter reflectors and measured the three successive layers of asphalt. The finish of the stabilised AP65 subbase was often uneven and made attaching the 300mm diameter reflectors difficult. Occasionally construction activities dislodged some of the reflectors before they could be paved over. WSP designed and 3D printed dowels that were glued to the bottom of the reflector and anchor fixed into the stabilised granular pavement. This significantly reduced the amount of glue required to hold the reflectors and almost completely eliminated the loss of reflectors caused by construction activities.

Figure 1 – 300mm reflector with the 3D printed dowel attached

WSP have since found a supply of off the shelf dowels and are currently using the larger of the two shown in the photograph below.

Figure 2 – Commercially available dowels

In section across the pavement, the initial thinking was to place reflectors in the middle and outer edges of each paving run. With reflectors placed at 40m cross section intervals it was too difficult to place and maintain seven reflectors so the layout was changed to placing a reflector near the middle of each run reducing the number of reflectors to three for each cross section. The general layout configuration is shown in the following diagram.

In the locations where the 300mm reflectors were dislodged, WSP used the 120mm diameter reflectors, placed on top of the AC20 layer and were able to measure the thickness of the AC14 layer and then the Epoxy Modified Open Graded Porous Asphalt (EMOGPA) wearing surface.

To provide greater coverage of the EMOGPA wearing surface thickness, 70mm reflectors were placed on top of the AC14 on cross-sections between the 300mm reflectors. This provided thickness measurements at 20m intervals.

The MIT-SCAN-T3 enables the quick location of the reflectors and then, the GPS located time stamped asphalt thickness reading is taken and recorded electronically. Data is transferred to the phone or tablet based MIT-SCAN-T3-APP, which enables you to:

  • Review the current measurements
  • Manage your measurement data
  • Create and send reports

Data can also be transferred to the PC-based MIT-Project-Software for data storage, presentation and geo-positioning of results.

The benefit of using the MIT-SCAN-T3 compared with traditional layer thickness measurement is that a very comprehensive coverage of asphalt thickness can be produced without cutting any core holes in the asphalt.

Cores may need to be cut to measure air void compliance in the asphalt, but if calibrated Nuclear Density Meter (NDM) thin lift gauge results are acceptable, or there is not a requirement to measure air voids, then there is no need to complete any destructive compliance measurements.

Other significant benefits of using the MIT-SCAN-T3 is the saving in time, personnel, and equipment to compile the layer thickness results.

Time is saved as the scanning can be completed as soon as the asphalt is sufficiently cool to run the MIT-SCAN-T3 over the surface. There is no need to wait until the asphalt is sufficiently cold enough to core.

The personnel saving is that the scanning can be completed quickly and efficiently by one person using the MIT-SCAN-T3. Coring would take much longer and would generally require two Laboratory technicians to complete the coring safely.

The equipment saving is the simplicity of use and cost of the MIT-SCAN-T3 compared to the use and cost of a coring rig.

I have known the team at Insitutek for over ten years. Their professionalism, positivity and enthusiasm for their work is outstanding and I am pleased to recommend them.

Greg Adamson

Geotechnical Engineering

We are using the PANDITO DCP for Level 1 site supervision, it’s very portable and we find it handy for flying into sites.

Stephen Flux

Principal Geotechnical Engineer at WANT Geotechnics

Insitutek is our partner overseas for our test equipment. Ask them for a presentation or training for our products. I am sure you will be satisfied. They are a reliable and very kindly partner.

Matthias Weingart

Anix GmbH

Insitutek Blogs

Compaction is one of the most important processes in pavement construction and, done well, leads to long-lasting pavement performance and reduced maintenance costs.

Our clients use Intelligent Compaction to create uniform efficient quantified compaction. Our Intelligent Compaction system provides:

We are delighted to officially announce our Ground Improvement portfolio.

For the last three years, we have been working on extending our offer from, just, in situ testing to testing and improving in situ conditions.

With our ground improvement portfolio, our focus is delivering more sustainable outcomes. Here is what we offer:

On 2 August 2024, geomechanics professionals gathered in Canberra for the Australian Geomechanics Society ACT Insitu Testing Practical Workshop. The event focused on practical demonstrations of key insitu testing methods, including Cone Penetration Testing (CPT), Static Plate Load Test (PLT), Dynamic Probing Super Heavy (DPSH), Light Weight […]